Contracts will be financed with the proceeds of a loan from the European Bank for Reconstruction and Development, the Tenders Electronic Daily (TED) said on its website.
The project will require the procurement of the following goods, works and services:
-Supply and installation of equipment for sub-stations,
-Supply and installation of remote monitoring, video supervision, controlling and adjustment of sub-stations,
-Closing of optical network in the transmission grid and preparation of a model for maximum utilization,
-Rehabilitation of 110 kilovolt (kV) Overhead Transmission Line (OHTL) and
-Consulting services to the Project Implementation Unit (PIU).
($=0.7758 euro)