July 23 (SeeNews) - The Bulgarian unit of U.S. power corporation ContourGlobal, which operates thermal power plant (TPP) Maritsa East 3, said that it has signed a 21.5 million levs ($12.3 million/11.0 million euro) construction works contract with local Energoremont Galabovo.
The deal was signed on July 4, ContourGlobal Maritsa East 3 said in a notice last week.
Energoremont Galabovo filed the only bid in the procedure for awarding the contract.
The 908 MW ContourGlobal Maritza Iztok 3 is 73%-owned by ContourGlobal, with the Bulgarian state-owned National Electricity Company holding the remaining 27% stake.
(1 euro = 1.95583 levs)