July 6 (SeeNews) - Serbian state-owned company Infrastruktura Zeleznice Srbije has invited tenders for the rehabilitation of electrotechnical infrastructure on Corridor X rail lines, the European Bank for Reconstruction and Development (EBRD) said.
The project includes the rehabilitation of electrotechnical infrastructure on the lines of railway node Belgrade and sections Stara Pazova-Sid, Resnik-Lapovo and Mala Krsna-Velika Plana, the EBRD said in a notice posted on its website.
The contract’s time for completion is 400 days. Tenders must be delivered until August 22, 2018, the EBRD said.
To be qualified for the award of a contract, tenderers must have a minimum average annual construction turnover of 5 million euro ($5.9 million) within the last three years, the bank added.
Infrastruktura Zeleznice Srbije was established as a joint stock company in 2015, as a part of the reorganisation implemented in railway operator Zeleznice Srbije which saw the uncoupling of the different sectors into separate companies.
($ = 0.853706 euro)