February 24 (SeeNews) - Bulgaria's state-owned coal-fired thermal power plant (TPP) Maritsa Iztok 2 said on Monday that it has awarded a 5 million levs ($2.8 million/2.6 million euro) contract for repair of parts of turbines and electric generators to a local tie-up.
The winning tie-up comprises Bright Engineering and Turbo Machine Bulgaria, TPP Maritsa Iztok 2 said in a notice.
The contract was signed on January 31, according to the notice.
The Bright Engineering-Turbo Machine Bulgaria tie-up submitted the sole offer in the tender for the contract.
According to registry agency data, both companies hold 50% interest in the tie-up.
TPP Maritsa Iztok 2 has eight operating units with a total installed capacity of 1,620 MW.
(1 euro = 1.95583 levs)
TETs Maritsa Iztok 2 EAD is among the biggest companies in SEE. You can download our SEE Top 100 ranking
here or subscribe to our free Top 100 newsletter