Bulgaria's TPP Maritsa 2 shuts down Unit 2 for maintenance

Author Mario Tanev
Bulgaria's TPP Maritsa 2 shuts down Unit 2 for maintenance Author: TPP Maritsa Iztok 2 / All rights reserved.

SOFIA (Bulgaria), February 22 (SeeNews) - Bulgarian state-owned thermal power plant (TPP) Maritsa Iztok 2 has shut down its 165 MW Unit 2 for maintenance, the Independent Bulgarian Energy Exchange (IBEX) said on Friday.

Works are scheduled to be completed on April 19, 2019, IBEX said in a notice. 

Earlier this month, TPP Maritsa Iztok 2 completed the planned maintenance of boiler 3 of its Unit 2.

Maritsa Iztok 2 has eight operating units with a total installed capacity of 1,620 MW. 