Bulgaria's ESO opens 2.3 mln euro tender for supply of power transformers

Author Mario Tanev
Bulgaria's ESO opens 2.3 mln euro tender for supply of power transformers Author: Nick Page. License: CC BY 2.0

SOFIA (Bulgaria), July 2 (SeeNews) - Bulgaria's Electricity System Operator (ESO) said that it has opened a 4.5 million levs ($2.6 million/2.3 million euro) tender for supply of six 50 MVA power transformers.

The power transformers should be delivered to power substations Obzor, Kableshkovo, Hristo Smirnenski and Samokov, ESO said in a tender notice on Monday.

The deadline for submitting offers is August 8.

Bids will be ranked based on price, which will form 50% of the final mark, and technical criteria.

(1 euro = 1.95583 levs)