April 24 (SeeNews) - Bulgaria's Electricity System Operator (ESO) said on Wednesday that it has launched a tender for awarding a contract for reconstruction of a section of 110 kV overhead transmission line Tundzha, near the city of Stara Zagora, worth an estimated 3.4 million levs ($1.9 million/1.7 million euro).
Works are expected to be completed within 120 days, ESO said in a tender notice.
The deadline for submitting offers is May 28.
Bids will be ranked solely based on price.
(1 euro = 1.95583 levs)