September 27 (SeeNews) - Albania’s power grid operator OSSH said on Wednesday it opened tender procedures for the reconstruction and expansion of a feeder in a substation in the southern city of Berat, estimated to cost 93 million leks ($923,000/874,000 euro).
The project involves the construction and reconstruction of multiple 10KV transmission line segments, as well as the reconstruction of various cabins and distribution network components using covered conductor cables, tender documents on the country’s open procurement portal show.
The project should be implemented within 170 days from the contract signing.
Potential bidders can submit their offers by October 18.
(1 euro = 106.447 Albanian leks)