TIRANA (Albania), September 25 (SeeNews) – Albania’s electricity distributor OSHEE said it has opened three tenders worth a total of 315 million leks ($2.9 million/2.5 million euro) for reconstruction works in the power substations in Tirana and Fier.
The maximum budget available for the works in Tirana is 292 million leks, while the cost of the projects in the southwestern city of Fier amounts to 23 million leks, OSHEE said in tender notices published by the country’s public procurement agency last week.
The bidding deadline for the tenders is October 22. Works in Tirana must be completed within 5 months after the signing of a contract whereas the works in Fier must be completed within 3 months.
(1 euro = 125.944 leks)